Kaskia Wellbeing Block

Discover the Kaskia Wellbeing Block


Located in the heart of Turku, the Kaskia Wellbeing Block combines modern housing, care services, and shared spaces to create a safe and welcoming community. Follow the construction progress on our website and see how the neighbourhood is taking shape.

General working hours for tasks causing noise and vibration

(according to the City of Turku decision of 16 June 2026, valid until 30 September 2026)

  • Construction and demolition work causing normal construction noise: weekdays 7:00–20:00

  • Earthworks and foundation works: weekdays 7:00–18:00

  • Piling works: weekdays 8:00–18:00
    (during the school summer holiday period until 10 August 2026: 9:00–18:00)

  • Drilling and blasting related to rock excavation: weekdays 8:00–18:00
    (during the school summer holiday period until 10 August 2026: 9:00–18:00)

  • Concrete crushing: weekdays 9:00–17:00

  • Heavy mechanical breaking works: weekdays 7:00–18:00
    (during the school summer holiday period until 10 August 2026: 9:00–18:00)
     

No work is carried out on public holidays or equivalent days.

The use of machinery and equipment causing disturbing noise, as well as heavy vehicle traffic, is prohibited between 22:00 and 7:00 unless there are compelling and justified reasons.

To reduce noise, vibration and dust, the site uses noise barriers, vibration monitoring and dust control measures.

Upon request, information on the timing of blasting operations will be provided in advance.

About the project

The Kaskia Wellbeing Block is being developed to meet future housing, care and community living needs in the heart of Turku.

It will combine homes, wellbeing services and shared spaces – creating a natural meeting place for everyday life.

The project is being developed by Stiftelsen Eschnerska Frilasarettet, a Turku-based foundation, in collaboration with C.G. Sundell’s Foundation.

Construction began in 2025, with the first buildings scheduled for completion in 2027.

Latest updates

Piling has been completed, and construction of the parking garage is entering a new phase

Construction site update – weeks 33-34

The Kaskia Wellbeing Block has reached an important milestone. The piling work for the Kaskia 55+ building has now been completed, and the construction of the car park is entering a new phase. At the same time, the stages of work causing vibration have largely been completed.

Work is ongoing on post-grouting the bedrock and constructing the watertight wall in the car park. The first section of the wall has been cast, and work on the second section is beginning on the Vuorikatu side. Meanwhile, formwork for the parking garage roof structure is underway.

The first concrete slab for the garage will be poured on Tuesday, 18 August. Due to the technical requirements of this process, work will begin exceptionally early at 6:00 a.m., but this stage of the work is not expected to generate significant noise.

Work ongoing on Tower Building and social/health centre

Rendering of the Tower Building façades is progressing, and interior construction is on schedule.

Construction of the future social and health centre is also progressing according to plan.

Updated traffic arrangements

The updated construction site layout plan included traffic arrangements is available on the website

A new lifting area on Itäinen Pitkäkatu has reduced the need for heavy lifting operations on Kaskenkatu. Due to the installation of the construction lift, the work area on Sirkkalankatu has also been extended.

However, occasional concrete pumping and unloading operations will still need to be carried out on Kaskenkatu. Temporary traffic arrangem

Latest updates

The construction site camera is once again operational, allowing progress on the site to be followed via the website.

We would like to warmly thank our neighbours for the feedback received through the website during the summer. Your feedback helps us continue to improve communication about the construction project. We also thank our neighbours for their patience throughout the construction works.

yesterday hrs 13:03

Site access

Access to the construction site is strictly prohibited without permission.
Only authorised site personnel may enter the area.
 

Contact

For questions about the project, traffic arrangements, or site updates, please contact:

Managing Director (Eschner Foundation)
Jukka Sjösten
+358 50 352 4906 
jukka.sjosten@eschner.fi

Head of Communications and Grants (Eschner Foundation)
Gunilla Sjöberg
+358 40 515 1537
gunilla.sjoberg@eschner.fi